Melbourne/meeting 27 September 2007
From 2007.igem.org
< Melbourne(Difference between revisions)
Line 30: | Line 30: | ||
*Phil: Gas vesicles progress/design/plan - needs? | *Phil: Gas vesicles progress/design/plan - needs? | ||
- | **Ligation P48J (SpeI & PstI digested) to PCR(GvpL) | + | **Ligation P48J (SpeI & PstI digested) to PCR(GvpL) -Failed |
- | **Ligation P48J (SpeI & PstI digested) to PCR(GvpB to GvpU inclusive)(XbaI and PstI digested) | + | **Ligation P48J (SpeI & PstI digested) to PCR(GvpB to GvpU inclusive)(XbaI and PstI digested)-Failed |
+ | ***high background vector only control, and low ligation colony counts (Repeated unfortunately). | ||
+ | ****Think single cut of vector being repaired in cell for background. | ||
+ | ****Think Ligation producing linear that cant recircularise reducing background in ligation plates. | ||
+ | ****Think circular ligation of large plasmid rare and not affecting results significantly. | ||
+ | ****Ran test on P48J digestion 1uL 1 hour 37deg showed PstI incomplete in buffer 2 + BSA | ||
+ | ****Performed P48J 16hr 37deg double digest & Sequencial digest in buffer 2 then 3 plating to check background, with and without quick ligase. | ||
+ | ***Smaller GvpL plasmid showed *10 colony numbers cf background with overnight ligation protocol. | ||
+ | ***No increase in numbers with 5 minute ligation. | ||
+ | ****Think ligase affecting transformation efficiency. | ||
+ | ****Running test of effect of ligase on transformation efficiency of control plasmid pUC18. | ||
+ | |||
**Buoyancy experiment needs repeating | **Buoyancy experiment needs repeating | ||
**Other parts required from kit->glycerol stocks: B034 (P1-3O) , B0015 (P1-1I or P3-3O), J61034 (P4-8F or 8H) | **Other parts required from kit->glycerol stocks: B034 (P1-3O) , B0015 (P1-1I or P3-3O), J61034 (P4-8F or 8H) | ||
Line 43: | Line 54: | ||
**Suggested Chris contact Lisa Hayes in chem eng re promotion. | **Suggested Chris contact Lisa Hayes in chem eng re promotion. | ||
- | *Phil: Administrative Timetable: ( | + | *Phil: Administrative Timetable: (3 Weeks to go) |
*Chris: Next years Comp Plan/preparations | *Chris: Next years Comp Plan/preparations | ||
Line 57: | Line 68: | ||
==5:00 End == | ==5:00 End == | ||
+ | |||
+ | ==Igem Administrative Timetable:== | ||
+ | |||
+ | {|border="1" | ||
+ | |||
+ | |12 October || Final team rosters due. Jamboree attendance fees due $100USD per team member USD$225 for others. | ||
+ | |||
+ | |- | ||
+ | |||
+ | |19 October|| Registration with late fee USD $50 goes off line. | ||
+ | |||
+ | |- | ||
+ | |||
+ | |26 October|| Project and wiki & part documentation frozen, DNA received USA. | ||
+ | |||
+ | |- | ||
+ | |||
+ | |3-4 November || iGEM Competition Jamboree, MIT, USA. | ||
+ | |||
+ | |} | ||
+ | |||
+ | |||
+ | |||
+ | . | ||
+ | |||
+ | |||
+ | |||
+ | *re prism :Edmund optics:VIS60 Schott veril linear variable interference filter SGD$1600 25mm wide 60mm long linear 400nm-700nm (contact sheet) | ||
+ | N47-279 eqilateral prism 35mm long 35mm face SGD$162 | ||
+ | |||
+ | |||
+ | |||
+ | == Documentation wiki status 115+ hours work outstanding:== | ||
+ | |||
+ | **Priority should be on plans and experimental report analysis and conclusions-----Alisa . | ||
+ | |||
+ | **Equipement: | ||
+ | |||
+ | *** MissingLas3000 method (in lab notebook) 2h | ||
+ | |||
+ | *** Missing DNA measurement protocol (eppendorf) 1h | ||
+ | |||
+ | **Reagents pages incomplete: 24h | ||
+ | |||
+ | ***Some location pictures not finished or uploaded. 12h | ||
+ | |||
+ | *** Some newer reagents not entered. 8h | ||
+ | |||
+ | **Secondary reagents pages not made: | ||
+ | |||
+ | *** LB, Plates, TAE , NZY+ Broth 3h | ||
+ | |||
+ | **Protocol part: | ||
+ | |||
+ | *** No connections from Protocols to reagents. 3h | ||
+ | |||
+ | *** Ligation protocol missing 2h | ||
+ | |||
+ | **Lab notebook: no entries after 19 JUly 16h | ||
+ | |||
+ | *** Format uses too many lines to see connections between days. 2h | ||
+ | |||
+ | *** Latter part missing links 2h | ||
+ | |||
+ | *** Can table of contents be restricted to date level? 4h | ||
+ | |||
+ | **Experimental reports: | ||
+ | |||
+ | *** Lacks discussion/conclusion 10h | ||
+ | |||
+ | *** Ligation experiment missing | ||
+ | |||
+ | *** Lattest few gells not marked up and entered. 20h | ||
+ | |||
+ | **Project overview link broken 1h | ||
+ | |||
+ | **Background: | ||
+ | |||
+ | *** Blue light theory missing , 5h | ||
+ | |||
+ | *** Red photo sensor to GFP test harness missing. 5h | ||
+ | |||
+ | **Plan: Only Gas vesicles plan entered. | ||
+ | |||
+ | |||
+ | |||
+ | {|border="1" | ||
+ | |||
+ | !Individual!!Desired time committment | ||
+ | |||
+ | |- | ||
+ | |||
+ | |Pat|| About 4h/wk Monday afternoon or Tuesday morning | ||
+ | |||
+ | |- | ||
+ | |||
+ | |Alisa|| About 4h/wk - Thursday afternoon | ||
+ | |||
+ | |- | ||
+ | |||
+ | |Jan || About 10h/pw - flexible weekday mornings | ||
+ | |||
+ | |- | ||
+ | |||
+ | |Phil || About 18h/pw - Thursday morning, Friday, Saturday or Sunday, | ||
+ | |||
+ | |} |
Latest revision as of 04:29, 27 September 2007
Contents |
3:30 Action points from last meeting:
- Alisa: Get plan for blue light on wiki (from 10 Aug). Alisa has done a plan but this is not on Wiki.
3:35 Status Reports: (5 minutes each including any discussion)
- Pat : Red light receptor progress/design/plan- needs?
- M30109: Must construct from scratch plan to be produced by Pat.
- craig seqenced Cph8 from M30109 first part present
- Cph8 from initial plate not functional
- This is then drives RBS-ComP-term
- RBS-ComP -done
- Also required is ConstitutiveProm-RBS-ComA-term
- RBS-ComA-term -done
- M30109: Must construct from scratch plan to be produced by Pat.
- Jan & Alisa: Blue light receptor design/plan progress - needs?
- ComP and SopII conbined at variouse points by using 4 primer stiching:
- Comp P forward
- SopII reverse
- ComP-SoPII overlap sense
- ComP-SopII overlap antisense
- Note that there are 7 different stiching pairs that result in combination at different points.-Done
- The product is then combined with RBS -Done
- Sequencing being performed Friday
- Then transcription terminator
- The constitutive promotor to create protein generator part.
- Also Required is reporter construct PsfPromoter-RBS-LacZ-term
- Only three colonies pSFR8 grew in LB
- ComP and SopII conbined at variouse points by using 4 primer stiching:
- Phil: Gas vesicles progress/design/plan - needs?
- Ligation P48J (SpeI & PstI digested) to PCR(GvpL) -Failed
- Ligation P48J (SpeI & PstI digested) to PCR(GvpB to GvpU inclusive)(XbaI and PstI digested)-Failed
- high background vector only control, and low ligation colony counts (Repeated unfortunately).
- Think single cut of vector being repaired in cell for background.
- Think Ligation producing linear that cant recircularise reducing background in ligation plates.
- Think circular ligation of large plasmid rare and not affecting results significantly.
- Ran test on P48J digestion 1uL 1 hour 37deg showed PstI incomplete in buffer 2 + BSA
- Performed P48J 16hr 37deg double digest & Sequencial digest in buffer 2 then 3 plating to check background, with and without quick ligase.
- Smaller GvpL plasmid showed *10 colony numbers cf background with overnight ligation protocol.
- No increase in numbers with 5 minute ligation.
- Think ligase affecting transformation efficiency.
- Running test of effect of ligase on transformation efficiency of control plasmid pUC18.
- high background vector only control, and low ligation colony counts (Repeated unfortunately).
- Buoyancy experiment needs repeating
- Other parts required from kit->glycerol stocks: B034 (P1-3O) , B0015 (P1-1I or P3-3O), J61034 (P4-8F or 8H)
- Pat to provide these.
3.55 New Agenda Items:
- Sally Grass (chemical and biochemical engineering):
- interested in signal transduction.
- moving to lab in bio21.
- will help promote next years comp
- Suggested Chris contact Lisa Hayes in chem eng re promotion.
- Phil: Administrative Timetable: (3 Weeks to go)
- Chris: Next years Comp Plan/preparations
- Slide prepared
- Alisa: To make competent cells to replace Joes
- Alisa: Tshirt should be simple based on Melb Uni logo, will propose a design
- Paul: suggested Ian Potter foundation may provide travel funding
- Next meeting: <b/> 27th September (Thurs) 3.30PM.
5:00 End
Igem Administrative Timetable:
12 October | Final team rosters due. Jamboree attendance fees due $100USD per team member USD$225 for others. |
19 October | Registration with late fee USD $50 goes off line. |
26 October | Project and wiki & part documentation frozen, DNA received USA. |
3-4 November | iGEM Competition Jamboree, MIT, USA. |
.
- re prism :Edmund optics:VIS60 Schott veril linear variable interference filter SGD$1600 25mm wide 60mm long linear 400nm-700nm (contact sheet)
N47-279 eqilateral prism 35mm long 35mm face SGD$162
Documentation wiki status 115+ hours work outstanding:
- Priority should be on plans and experimental report analysis and conclusions-----Alisa .
- Equipement:
- MissingLas3000 method (in lab notebook) 2h
- Missing DNA measurement protocol (eppendorf) 1h
- Reagents pages incomplete: 24h
- Some location pictures not finished or uploaded. 12h
- Some newer reagents not entered. 8h
- Secondary reagents pages not made:
- LB, Plates, TAE , NZY+ Broth 3h
- Protocol part:
- No connections from Protocols to reagents. 3h
- Ligation protocol missing 2h
- Lab notebook: no entries after 19 JUly 16h
- Format uses too many lines to see connections between days. 2h
- Latter part missing links 2h
- Can table of contents be restricted to date level? 4h
- Experimental reports:
- Lacks discussion/conclusion 10h
- Ligation experiment missing
- Lattest few gells not marked up and entered. 20h
- Project overview link broken 1h
- Background:
- Blue light theory missing , 5h
- Red photo sensor to GFP test harness missing. 5h
- Plan: Only Gas vesicles plan entered.
Individual | Desired time committment |
---|---|
Pat | About 4h/wk Monday afternoon or Tuesday morning |
Alisa | About 4h/wk - Thursday afternoon |
Jan | About 10h/pw - flexible weekday mornings |
Phil | About 18h/pw - Thursday morning, Friday, Saturday or Sunday, |