5:30 Action points from last meeting:
- Alisa: Wiki "Parts_used status" up to date? -(outstanfding from 19/7/07)
- Jan: Lecture Timetables spread sheet complete: attached.
- Phil: Status of #BBa-M30109 & #BBa-V1012 = "will ship this week".
- Jan: Production of sequence for blue light receptor? " -designed
5:45 Status Reports: (5 minutes each including any discussion)
- Alisa: Ligation experiments progress.
- Problem: 1.2KB genes between biobrick forward & reverse primers not being visualised in colony PCR with 1.5min extn time. (300bp fragments do amplify)
- - craig to try and repeat.
- - Alisa: has digestion in progress as alternative diagnostic to prove if problem is ligation or PCR.
- - Alisa: believes alkaline phosphatase damage is cause of problem.
- Problem: 1.2KB genes between biobrick forward & reverse primers not being visualised in colony PCR with 1.5min extn time. (300bp fragments do amplify)
- Alisa: Red light receptor progress/design/plan- needs.
- Plan to be completed to be put on wiki this week, estimated at six weeks duration.
- Phil would like to see lacZ coliphotography parts available for tests due to higher sensitivity of enzyme output.
- Jan: Blue light receptor design/plan - needs.
- design completed, Plan to be completed and put on wiki this week -Jan
- Theory to be put on the wiki this week - Jan,-Alisa to review
- ComA to be ordered by tuesday under discount plan
- ComP fusion to be ordered ASAP.
- Phil: Gas vesicles progress/design/plan - needs.
- Plan up to basic biobrick complete,
- Primers not requested for Friday delivery so cant proceed this week end.
- Mutagenesis primers will be redesigned by hand for delivery next Friday.
- Biobrick prefix/sufix primers to be designed this week.
- Plan for support parts/test harness required.
- Some items require ordering,round bottom falcon tubes, or manufacture NZY broth, blue/white plate.
- Lac promotor and antibiotic death plasmids required.
- Pat:
- Will transform, growup and prepare glycerol stocks of death plasmid in DB3.1 this week.
- Kasia: Documentation progress vs last report/ new problems/ needs.-No report
6.15 New Agenda Items:
- Phil: Individuals desired time commitment:
Individual | Desired time committment |
---|---|
Pat | About 4h/wk Monday afternoon or Tuesday morning |
Alisa | About 4h/wk - Thursday afternoon |
Jan | About 10h/pw - flexible weekday mornings |
Phil | About 18h/pw - Thursday morning, Friday, Saturday or Sunday, |
- Phil: Administrative Timetable: (12 Weeks to go)
- Fab request & project description by Tuesday 31 July.
- "Produce and characterize buoyant bacteria and light receptor components of coliforming system."
- Next meeting: <b/> 6th August (Monday) 1.15PM agreed but latter changed to 3rd Aug (Friday) 5:30PM.
6:30 End
Igem Administrative Timetable:
1 August | Team project descriptions due. |
1 September | Final team rosters due. |
1 September | Jamboree attendance fees due $100USD per team
member. |
26 October | Project and part documentation due DNA received USA. |
26 October | BioBrick Part DNA received by the Registry. |
3-4 November | iGEM Competition Jamboree, MIT, USA. |
.
Documentation wiki status:
- Priority should be on plans and experimental report analysis and conclusions-----Alisa .
- If only Pat & Alisa doing lab work not much documentation needed.
- Equipement:
- MissingLas3000 method (in lab notebook)
- Missing DNA measurement protocol (eppendorf)
- Reagents pages incomplete:
- Some location pictures not finished or uploaded.
- Some newer reagents not entered.
- Secondary reagents pages not made:
- LB, Plates, TAE , NZY+ Broth
- Protocol part:
- No connections from Protocols to reagents.
- Ligation protocol missing
- Lab notebook:
- Format uses too many lines to see connections between days.
- Latter part missing links
- Can table of contents be restricted to date level?
- Experimental reports:
- Lacks discussion/conclusion
- Ligation experiment missing
- Lattest few gells not marked up and entered.
- Project overview link broken
- Background:
- GFP missing ,
- Red photo sensor to GFP test harness missing.
- Plan: Only Gas vesicles plan entered.