5:30 Action points from last meeting:
- Alisa: Wiki "Parts_used status" up to date? -(outstanfding from 19/7/07)
- Jan: Lecture Timetables spread sheet complete: attached.
- Phil: Status of #BBa-M30109 & #BBa-V1012 = "will ship this week".
- Jan: Production of sequence for blue light receptor? " -designed
5:45 Status Reports: (5 minutes each including any discussion)
- Alisa: Ligation experiments progress.
- Alisa: Red light receptor progress/design/plan- needs.
- Plan to be completed to be put on wiki this week
- Jan: Blue light receptor design/plan - needs.
- design completed, Plan to be completed and put on wiki this week
- Phil: Gas vesicles progress/design/plan - needs.
- Plan up to basic biobrick complete,
- Primers not requested for Friday delivery so cant proceed this week end.
- Mutagenesis primers will be redesigned by hand for delivery next Friday.
- Biobrick prefix/sufix primers to be designed this week.
- Plan for support parts/test harness required.
- Kasia: Documentation progress vs last report/ new problems/ needs.-No report
6.15 New Agenda Items:
- Phil: Individuals desired time commitment?
eg 12hrs per week equiv to an extra subject, or 3 hrs on wed afternoon only...
- Phil: Administrative Timetable: (12 Weeks to go)
Fab request & project description by Tuesday 31 July. "Produce and characterize buoyant bacteria and light receptor components of coliforming system."
6:30 End
Igem Administrative Timetable:
- 31 July Must lodge fabrication request to receive quota.
- 1 August Team project descriptions due.
- 1 September Final team rosters due.
- 1 September Jamboree attendance fees due $100USD per team
member.
- 26 October Project and part documentation due DNA received USA.
- 26 October BioBrick Part DNA received by the Registry.
- 3-4 November iGEM Competition Jamboree, MIT, USA.
.
- Some items require ordering,round bottom falcon tubes, or manufacture NZY broth, blue/white plate.
- Lac promotor and antibiotic death plasmids required.
- Primers on critical path -------phil to complete ASAP.
- Jan Status report on Blue light sensor and light box apperatus, lead time on DNA fabrication?
- Plan to have biobrick fabricated (up to 3Kb on fast turnarround= 525USD.)
- Adhesion: to be abbandoned for this year, unless clever idea comes to mind.
- Documentation wiki status:
- Priority should be on plans and experimental report analysis and conclusions-----Alisa .
- If only Pat & Alisa doing lab work not much documentation needed.
- Equipement:
- MissingLas3000 method (in lab notebook)
- Missing DNA measurement protocol (eppendorf)
- Reagents pages incomplete:
- Some location pictures not finished or uploaded.
- Some newer reagents not entered.
- Secondary reagents pages not made:
- LB, Plates, TAE , NZY+ Broth
- Protocol part:
- No connections from Protocols to reagents.
- Ligation protocol missing
- Lab notebook:
- Format uses too many lines to see connections between days.
- Latter part missing links
- Can table of contents be restricted to date level?
- Experimental reports:
- Lacks discussion/conclusion
- Ligation experiment missing
- Lattest few gells not marked up and entered.
- Project overview link broken
- Background:
- GFP missing ,
- Red photo sensor to GFP test harness missing.
- Plan: Only Gas vesicles plan entered.